CONSTRUCTION CLEANING & SWISS CONTRACT LAW

Post-Construction Cleaning per SIA 118: Phases from Rough to Final Clean & Legal Acceptance

Coordination between site management, trades, and cleaning: Preventing cement residue, blade scratch damage to glass, and legally secure handover under Swiss contract of enterprise.

9 min read
Updated: 2026-10-11
Verified Swiss regulatory sources
Turnkey final post-construction cleaning of a modern new building in Zurich before SIA 118 handover acceptance
Final post-construction cleaning per SIA 118: Dust-free, residue-free handover to developers and tenants.Mondar Construction Cleaning / SIA Standards
Instant Assessment on WhatsApp

Questions regarding Swiss regulatory compliance or an upcoming inspection? Reach our Zurich operations desk directly on WhatsApp for immediate guidance.

WhatsApp (+41 44 513 77 66)
STANDARDS & TECHNICAL SPECIFICATIONS

The 3 Phases of Construction Cleaning per BKP 287 & SIA 118

Clear coordination of trades from structural shell to turnkey key handover

01Shell Construction

Rough Construction Clean

Continuous removal of construction debris, timber scraps, and packaging to ensure site occupational safety (BauAV).

02Fit-Out Phase

Interim Construction Clean

Industrial vacuuming and preparation of substrates before laying parquet, screed, or epoxy coatings.

03Pre-SIA Acceptance

Final Post-Construction Clean

Gentle removal of cement film, protective films, and fine particulate dust adhering to SIGaB glass guidelines.

04Handover

Turnkey Handover

Joint inspection with site management and client; drafting and signing the formal acceptance protocol.

2. The Costliest Damage: Cement Film, Glass Scratches (SIGaB) & Acid Etching

Site cleaning requires sound chemical and materials knowledge. Unqualified cleaning crews regularly cause six-figure damage to new developments:

  • 1. Glass Scratches from Dry Scraping: Removing plaster splatters with dry utility blades causes irreversible hairline scratches on float or tempered safety glass (ESG). Under Swiss Institute for Glass in Building (SIGaB) directives, glass scrapers must only be operated wet with ample lubrication and pristine blades.
  • 2. Acid Damage on Natural Stone & Fixtures: Cement film removers are often acidic. If acidic chemistry touches calcareous stone (marble, travertine, terrazzo) or chrome-plated mixers, surfaces become permanently etched and dull.
  • 3. Baked-In Protective Films: When factory protective films on window frames, lift-and-slide doors, or stainless steel cladding are left exposed to solar UV radiation too long, adhesives bake into surfaces and require extreme specialist effort to strip.

Essential Advice for Site Managers & General Contractors

Always request proof of commercial third-party liability insurance from cleaning contractors before work commences, specifically verifying coverage for work-related processing damage under SIA 118.

3. The Three Phases in Detail: BKP 287 Systematics

Successful building handover depends strictly on adhering to the correct chronological sequence of cleaning phases:

  • Rough Construction Clean: Ongoing disposal of rubble, mortar residue, drywall scraps, and pallets. Safeguards health and safety under SUVA BauAV and stops debris entering ventilation ducts or floor screeds.
  • Interim Construction Clean: Selective deep cleaning prior to delicate follow-up trades. For instance, prior to parquet adhesive application or epoxy coating, substrates must be industrially vacuumed to prevent void pockets.
  • Final Post-Construction Clean (Turnkey Clean): Conducted approximately 2 to 4 days before official handover. Encompasses window cleaning including all frame rebates, streak-free polishing of sanitary ware, dusting of switches, light fixtures, and skirting boards, plus material-specific initial care of flooring.

4. Construction Cleaning with Mondar in the Greater Zurich Area

Mondar coordinates experienced, certified Swiss cleaning companies for construction projects of any scale — from high-spec luxury residential renovations to large developments across Canton Zurich.

Our partners work strictly to SIA 118, hold required occupational safety certifications (SUVA/EKAS), and guarantee timely handover readiness.

SWISS QUALITY STANDARD

SIA 118 Checklist for Final Construction Cleaning & Acceptance

Compliant with guidelines from the Swiss Homeowners Association (HEV) and Tenants' Association (MV).

0 / 9 points completed0%

Preparation & Building Protection

3 Inspection points

Glass & Surface Cleaning

3 Inspection points

Floors & Sanitary

3 Inspection points

Legal Sources & Verified Standards

StandardSIA 118 (Art. 157 ff. Acceptance of Works)
SIA Standard 118: General Conditions for Construction Works

Swiss standard contractual terms for building handover, defect notices, and transfer of risk

StandardSR 220
Swiss Code of Obligations (Contract for Work, Art. 363–379 CO)

Statutory regulation of contractor duties and liability for construction defects

StandardSIGaB Guideline: Cleaning of Architectural Glass
Swiss Institute for Glass in Building (SIGaB)

Technical rules to prevent mechanical surface damage during final site handover cleans

StandardSR 832.311.141
Ordinance on Occupational Safety in Construction (BauAV)

Federal health and safety regulations on Swiss building sites